Design Review of road design projects
Design Review works are among our routine’s undertakings making use of senior professional of Pure Consulting Engineer’s design team as a separate contract or part of the supervision contract. We have best facilities and equipment from setting out stage helping verification of the primary and secondary control points established at the design stage to test the soundness and coherence of the original design data against the national grid. Consequently, the design data will be exported considering all assumptions the original design founded on and then converting to the state of art, up-to-date satellite imageries and mapping facilities. Despite the scrutiny making use of design software that our experts are well versed, we assess beyond verification of fitness of the road design delivery to the intended purpose. Thus, all team fellows of our senior design professionals will accordingly take their respective responsibilities headed by the team leader to perform according to the planed arrangement, Design quality checklists working hard for meeting time, cost and quality milestones to the service contract Terms of references.
Project Location
Southern National nationalities people Regional State.
Client
Ethiopian Road Authority (ERA)
Project Duration
6 September, 2011 — 06 March, 2014
Project Name
Yabello-Metagefersa-Shakiso Road Upgrading Project. Contract 1: Yabele-MetagefersaOblo, Lot II: km 36-km 75.
Description
Design Review, construction supervision, Contract Administration and pertinent service works to implement in accordance to works contract, design drawings and bill of quantity.
Project Location
Southern National nationalities people Regional State.
Client
Ethiopian Road Authority (ERA)
Project Duration
August 12, 2011 — July 10, 2017
Project Name
Arbaminch – Kamaba – Sawla Road Project Lot II: Belta – Otolo
Description
Asphalt Double surface Treatment DS4 being constructed by DiribaDefersha General Contractor and the length of the road is 34.87 km the total work completed to date is 99.07% of the total to which the total project cost is ETB 748,099,415.74